Hardware High Level Overview

By gugan73715 · Last updated: September 18, 2026 · Created: September 16, 2026

Design Timeline:

PCB Ownership Priority First Design Review Date Design Freeze Date
Flight Controller Gugan High 04/10/2026 18/10/2026
LiDAR PCB Gugan High 04/10/2026 18/10/2026
Backplane Ken High 11/10/2026 18/10/2026
Test Board Ken Medium 11/10/2026 18/10/2026
Custom Telemetry Radio GND Station PCB Annie Medium 08/11/2026 15/11/2026
ESC Gugan Medium 01/11/2026 15/11/2026
USB-C PD Charger DFT Gugan Medium 01/11/2026 15/11/2026
RTK-GNSS GND PCB Nick Low 01/11/2026 15/11/2026

Note: PCB Fabrication Order's are batched into two dates: 18/10/2026 and 15/11/2026. (Will be co-ordinated with COTS)